Luzon-Visayas HVDC bipolar operation - target Dec 2032
Mindoro-Panay 230 kV Interconnection - TDP 2041-2050; DOE now implementing it as a strategic project, NGCP considering accelerating (originally 2040 per NGCP) (2026-09-22)
Luzon-to-Cebu transfer: about 400 MW transmissible but only 200-250 MW reaching Cebu; first stage of new Cebu interconnection (+600 MW) moved up to 2029 from 2031 (2026-10-05)
One Mindoro Power Grid Development targeted for completion by 2027 (2026-09-07)
Pinagkunan: DOE Power Statistics 2025, tala ng NGCP, DOE retail rate sheet.