🗞️ News🏛️ Politics⚡ Electricity🏗️ Infrastructure⚡ Electricity · Luzon Capacity, demand, fuel mix, outages and prices on the three grids: Luzon, Visayas and Mindanao.
Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity Luzon: 98.53% households with electricity
98.53% ⚡ Luzon grid
Dependable capacity 20,340 MW
Peak demand (2025) 13,839 MW
Where the power comes from (2025)
Coal 56.9% Gas 24.2% Geothermal 4.8% Hydro 7.9% Solar 4.1% Wind 1.2%
Households with electricity 98.53%
Grid alerts in 2026 so far not published
Residential rate (Sep 2026) MERALCO (NCR, Luzon) ₱14.74
Grid links Mariveles-Hermosa-San Jose 500 kV line completed (2024-07) Batangas-Mindoro Interconnection - Stage 1 target Sep 2027, Stage 2 Dec 2030 Luzon-Visayas HVDC bipolar operation - target Dec 2032 Mindoro-Panay 230 kV Interconnection - TDP 2041-2050; DOE now implementing it as a strategic project, NGCP considering accelerating (originally 2040 per NGCP) (2026-09-22) Luzon-to-Cebu transfer: about 400 MW transmissible but only 200-250 MW reaching Cebu; first stage of new Cebu interconnection (+600 MW) moved up to 2029 from 2031 (2026-10-05) One Mindoro Power Grid Development targeted for completion by 2027 (2026-09-07)
⚡ Full power infographic →
Sources: DOE Power Statistics 2025, NGCP alert tallies, DOE retail rate sheet.