🏗️ Imprastruktura · Luzon

Mga tulay, dalan, riles, tugpahanan, pantalan, linya sa kuryente ug tubig: nahuman, ginatukod ug giplano.

AbraAlbayApayaoAuroraBataanBatanesBatangasBenguetBulacanCagayanCamarines NorteCamarines SurCatanduanesCaviteIfugaoIlocos NorteIlocos SurIsabelaKalingaLa UnionLagunaMarinduqueMasbateMetro ManilaMountain ProvinceNueva EcijaNueva VizcayaOccidental MindoroOriental MindoroPalawanPampangaPangasinanQuezonQuirinoRizalRomblonSorsogonTarlacZambales 6. Kaliwa Dam (New Centennial Water Source) · under construction62. North–South Commuter Railway (NSCR) · under construction25. New Manila International Airport (Bulacan) · under construction51. Metro Manila Subway (Phase 1) · under construction13. MRT Line 7 · under construction38. Guadalupe Bridge rehabilitation · planned84. Bataan–Cavite Interlink Bridge · approved47. SLEX Toll Road 4 (Sto. Tomas–Tiaong) · under construction79. Bicol International Airport · operational9
  1. 1

    🚆 Metro Manila Subway (Phase 1) under construction

    Ayon sa DOTr noong Hulyo 2026, mga 60% nang tapos ang subway at inaasahan ang demonstration run sa bahaging Valenzuela–Quirino pagsapit ng 2028.

    Metro Manila · target 2028 · [1] [2]

  2. 2

    🚆 North–South Commuter Railway (NSCR) under construction

    Ang 147-km na linyang Clark–Calamba ay 62% nang tapos noong Hulyo 2026; inilipat ng Malacañang ang buong operasyon sa ikatlong kwarter ng 2033, at unang bubuksan ang Valenzuela–Malolos sa Disyembre 2027.

    Pampanga, Bulacan, Metro Manila, Laguna · target 2033 · [1] [2]

  3. 3

    🚆 MRT Line 7 under construction

    Ang 23-km na linyang pinondohan ng San Miguel mula North Avenue hanggang San Jose del Monte, Bulacan ay 89% nang tapos noong Hulyo 2026, at target ang operasyon sa ikalawang kwarter ng 2027.

    Metro Manila, Bulacan · target 2027 · [1] [2]

  4. 5

    ✈️ New Manila International Airport (Bulacan) under construction

    Target ng San Miguel ang unang runway sa apat pagsapit ng katapusan ng 2028 at buong pagkumpleto bandang 2032, ngunit naaantala ito dahil kulang ang angkop na buhanging pantambak.

    Bulacan · ₱740.0 bilyon · target 2028 · [1] [2]

  5. 6

    💧 Kaliwa Dam (New Centennial Water Source) under construction

    Ang P15.3-bilyong dam na 60 metro ang taas at may 27.7-km na tunnel para sa 600 milyong litro ng tubig kada araw ay 26% nang tapos noong katapusan ng 2025, target sa 2028.

    Quezon · ₱15.3 bilyon · target 2028 · [1]

  6. 7

    🛣️ SLEX Toll Road 4 (Sto. Tomas–Tiaong) under construction

    Ayon sa datos ng DPWH noong Hunyo 2026, 43.70% ang Sto. Tomas–Makban, 77.42% ang Makban–San Pablo at 95.54% ang San Pablo–Tiaong.

    Batangas, Laguna, Quezon · [1]

  7. 8

    🌉 Guadalupe Bridge rehabilitation planned

    Ang rehabilitasyon ng tulay ng EDSA sa ibabaw ng Ilog Pasig, na uunahan ng mga detour bridge, ay maaaring ipagpaliban sa 2027 ayon kay dating DPWH Secretary Bonoan.

    Metro Manila · target 2027 · [1] [2]

  8. 9

    ✈️ Bicol International Airport operational

    Binuksan noong 2021 ang Bicol International Airport sa Albay.

    Albay · giablihan 2021 · [1]

Gikan sa DPWH, DOTr, NGCP ug mga balita; kahimtang sukad 2026-10-05. Matag item adunay gigikanan.