Abra Albay Apayao Aurora Bataan Batanes Batangas Benguet Bulacan Cagayan Camarines Norte Camarines Sur Catanduanes Cavite Ifugao Ilocos Norte Ilocos Sur Isabela Kalinga La Union Laguna Marinduque Masbate Metro Manila Mountain Province Nueva Ecija Nueva Vizcaya Occidental Mindoro Oriental Mindoro Palawan Pampanga Pangasinan Quezon Quirino Rizal Romblon Sorsogon Tarlac Zambales
6. Kaliwa Dam (New Centennial Water Source) · under construction 6 2. North–South Commuter Railway (NSCR) · under construction 2 5. New Manila International Airport (Bulacan) · under construction 5 1. Metro Manila Subway (Phase 1) · under construction 1 3. MRT Line 7 · under construction 3 8. Guadalupe Bridge rehabilitation · planned 8 4. Bataan–Cavite Interlink Bridge · approved 4 7. SLEX Toll Road 4 (Sto. Tomas–Tiaong) · under construction 7 9. Bicol International Airport · operational 9 1 🚆 Metro Manila Subway (Phase 1) under construction DOTr said in July 2026 the subway is about 60% complete, with a demonstration run on the Valenzuela–Quirino section expected by 2028.
Metro Manila · target 2028 · [1] [2]
2 🚆 North–South Commuter Railway (NSCR) under construction The 147-km Clark–Calamba commuter line was 62% complete in July 2026; Malacañang moved full operation to Q3 2033, with Valenzuela–Malolos to open first in December 2027.
Pampanga, Bulacan, Metro Manila, Laguna · target 2033 · [1] [2]
3 🚆 MRT Line 7 under construction The 23-km San Miguel-financed line from North Avenue to San Jose del Monte, Bulacan was 89% complete in July 2026, with operations targeted for Q2 2027.
Metro Manila, Bulacan · target 2027 · [1] [2]
4 🌉 Bataan–Cavite Interlink Bridge approved Land-approach packages of the 32.15-km Mariveles–Naic bridge across Manila Bay were awarded in Nov 2025 and Feb 2026; DPWH says construction will run past 2028.
Bataan, Cavite · [1] [2]
5 ✈️ New Manila International Airport (Bulacan) under construction San Miguel targets the first of four runways by end-2028 and full completion around 2032, but says a shortage of suitable fill sand is delaying work.
Bulacan · ₱740.0 billion · target 2028 · [1] [2]
6 💧 Kaliwa Dam (New Centennial Water Source) under construction The P15.3-billion, 60-m dam with a 27.7-km tunnel to supply 600 million litres a day to Metro Manila was 26% complete at end-2025, targeting 2028.
Quezon · ₱15.3 billion · target 2028 · [1]
7 🛣️ SLEX Toll Road 4 (Sto. Tomas–Tiaong) under construction DPWH data in June 2026 put the Sto. Tomas–Makban package at 43.70%, Makban–San Pablo at 77.42% and San Pablo–Tiaong at 95.54% complete.
Batangas, Laguna, Quezon · [1]
8 🌉 Guadalupe Bridge rehabilitation planned Rehabilitation of the EDSA bridge over the Pasig River, with detour bridges first, could be deferred to 2027 according to former DPWH Secretary Bonoan.
Metro Manila · target 2027 · [1] [2]
9 ✈️ Bicol International Airport operational Bicol International Airport in Albay opened in 2021.
Albay · opened 2021 · [1]
Compiled from DPWH, DOTr, NGCP and news reports; status as of 2026-10-05. Each item links its sources.